Question : A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?

Option 1: $\frac{33}{8}$

Option 2: $\frac{40}{9}$

Option 3: $\frac{41}{10}$

Option 4: $\frac{42}{11}$


Team Careers360 6th Jan, 2024
Answer (1)
Team Careers360 8th Jan, 2024

Correct Answer: $\frac{40}{9}$


Solution : Given:
A can do a piece of work in 8 days and B can do it in 10 days separately.
So, in 1 day A and B alone can do $\frac{1}{8}$ part and $\frac{1}{10}$ part of the work, respectively.
Now, together in 1 day they can do ($\frac{1}{8}$ + $\frac{1}{10}$) = $\frac{5 + 4}{40}$ = $\frac{9}{40}$ part of the work.
Therefore, A and B together can finish the work in (1 ÷ $\frac{9}{40}$) = $\frac{40}{9}$ days.
Hence, the correct answer is $\frac{40}{9}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books