7 Views

Question : A can do a piece of work in 8 days which B can destroy in 3 days. A has worked for 6 days, during the last 2 days of which B has been destroying; how many days must A work alone to complete the remaining work?

Option 1: $7\ \text{days}$

Option 2: $7\frac{1}{3}\ \text{days}$

Option 3: $7\frac{2}{3}\ \text{days}$

Option 4: $8\ \text{days}$


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: $7\frac{1}{3}\ \text{days}$


Solution : Time taken by A alone to do the work = 8 days
Part of work done by A alone in a day = $\frac{1}{8}$
Time taken by B alone to destroy the work = 3 days
Part of work destroyed by B alone in a day = $\frac{1}{3}$
Part of work done by A in 6 days = $\frac{6}{8}$
Part of work destroyed by B in last 2 days = $\frac{2}{3}$
Part of work completed after 6 days = $\frac{6}{8}-\frac{2}{3}$ = $\frac{18-16}{24}$ = $\frac{2}{24}$
Remaining part of work to be completed by A alone = $1-\frac{2}{24}$ = $\frac{22}{24}$
So, the number of days needed to complete the remaining work by A alone = $\frac{\frac{22}{24}}{\frac{1}{8}}$ = $\frac{22}{3}$ = $7\frac{1}{3}\ \text{days}$
Hence, the correct answer is $7\frac{1}{3}\ \text{days}$.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books