Question : A can do a task in 8 days, while B can do it in 18 days. In how many days will the work be completed if they both work on alternate days, starting with B?

Option 1: $11 \frac{1}{3}$ days

Option 2: $12 \frac{1}{3}$ days

Option 3: $10$ days

Option 4: $10 \frac{1}{3}$ days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 13th Jan, 2024

Correct Answer: $11 \frac{1}{3}$ days


Solution : Given: A can do a task in $8$ days.
B can do it in $18$ days.
Let the total work be the LCM of $(8, 18)$ i.e. $72$ units.
⇒ Efficiency of A $=\frac{72}{8} = 9$ units
⇒ Efficiency of B $=\frac{72}{18} = 4$ units
Work done by A and B in $2$ days $=(9 + 4) = 13$ units
Work done by A and B in 10 days when they work on alternate days $= 5 \times 13 = 65$ units
Remaining work  $= 72 -65 = 7$ units
B's work on the $11$ th day is $4$ units.
So, remaining work $= 7 -4 =3$ units
Time taken by A to complete $3$ units $=\frac{3}{9}=\frac{1}{3}$
Total time taken by A and B to complete the work $= 10 + 1 + \frac{1}{3}=11\frac{1}{3}$ days
Hence, the correct answer is $11\frac{1}{3}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books