Question : A can do a work in 6 days, which B alone can do in 8 days. In how many days they together can do it?

Option 1: $\frac{24}{7}$ days

Option 2: $\frac{25}{7}$ days

Option 3: $\frac{27}{4}$ days

Option 4: $\frac{22}{3}$ days


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $\frac{24}{7}$ days


Solution : One day's work of A = $\frac{1}{6}$
One day's work of B = $\frac{1}{8}$
One day's work of A and B together = $\frac{1}{6}+\frac{1}{8}$ = $\frac{4+3}{24}$ = $\frac{7}{24}$
$\therefore$ Together they can complete the work in ($1÷\frac{7}{24}$) = $\frac{24}{7}$ days
Hence, the correct answer is $\frac{24}{7}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books