3 Views

Question : A can do as much work in 4 days as B can do in 5 days and B can do as much work in 6 days as C in 7 days. In what time will C complete a piece of work that A can do in a week?

Option 1: $10\frac{5}{24}$ days

Option 2: $4\frac{4}{5}$ days

Option 3: $6\frac{8}{15}$ days

Option 4: $12\frac{6}{19}$ days


Team Careers360 25th Jan, 2024
Answer (1)
Team Careers360 26th Jan, 2024

Correct Answer: $10\frac{5}{24}$ days


Solution : A's 4-day work = B's 5-day work
The ratio time is taken by A and B = 4 : 5
B's 6-day work = C's 7-day work
The ratio of time taken by B and C = 6 : 7
Combining the two ratios, we get:
The ratio of time taken by A, B and C,
A : B : C = 4 × 6 : 5 × 6 : 7 × 5 = 24 : 30 : 35
The ratio efficiency of A : B : C = $\frac{1}{24}:\frac{1}{30}:\frac{1}{35} = 35:28:24$
Let one day's work of A, B, and C be 35, 28 and 24 units.
7 days work of A = $7\times 35 = 245$ units
245 units completed by C = $\frac{245}{24}=10\frac{5}{24}$
Hence, the answer is $10\frac{5}{24}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books