Question : A can do as much work in 4 days as B can do in 5 days and B can do as much work in 6 days as C in 7 days. In what time will C complete a piece of work that A can do in a week?
Option 1: $10\frac{5}{24}$ days
Option 2: $4\frac{4}{5}$ days
Option 3: $6\frac{8}{15}$ days
Option 4: $12\frac{6}{19}$ days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $10\frac{5}{24}$ days
Solution : A's 4-day work = B's 5-day work The ratio time is taken by A and B = 4 : 5 B's 6-day work = C's 7-day work The ratio of time taken by B and C = 6 : 7 Combining the two ratios, we get: The ratio of time taken by A, B and C, A : B : C = 4 × 6 : 5 × 6 : 7 × 5 = 24 : 30 : 35 The ratio efficiency of A : B : C = $\frac{1}{24}:\frac{1}{30}:\frac{1}{35} = 35:28:24$ Let one day's work of A, B, and C be 35, 28 and 24 units. 7 days work of A = $7\times 35 = 245$ units 245 units completed by C = $\frac{245}{24}=10\frac{5}{24}$ Hence, the answer is $10\frac{5}{24}$ days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A, B, and C working alone, can complete a job in 16, 24, and 36 days, respectively. In how many days can they complete the job if they work together?
Question : A can do a piece of work in 9 days, while B can do it in 12 days. A and B together can do the work in:
Question : P, Q, and R can complete a piece of work in 10 days, 15 days, and 20 days, respectively. If they work together, in how many days can they finish the same work?
Question : A, B, and C can do a job in 6 days, 12 days and 15 days respectively. After $\frac{1}{8}$th of the work is completed, C leaves the job. The rest of the work is done by A and B together. The time taken to finish the work is:
Question : P and Q together complete a job in $4 \frac{2}{5}$ days. R and S complete the same job in $4 \frac{8}{9}$ days. If P, Q, R, and S work together, how many days do they need to complete the same job?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile