4 Views

Question : A can do $\frac{1}{4}$th part of a work in 9 days. B can do $\frac{2}{3}$rd part of the same work in 28 days. Working together, in how many days can A and B complete the whole work?

Option 1: $\frac{262}{11}$ days

Option 2: $\frac{252}{13}$ days

Option 3: $\frac{261}{15}$ days

Option 4: $\frac{198}{17}$ days


Team Careers360 11th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $\frac{252}{13}$ days


Solution : Given: A can do $\frac{1}{4}$ part of a work in 9 days.
A does the whole work in $9\times 4=36$ days.
So, A's one day's work = $\frac{1}{36}$.
B can do $\frac{2}{3}$ part of the same work in 28 days.
B does the whole work in $28\times \frac{3}{2}=42$ days.
So, B's one day's work = $\frac{1}{42}$.
The number of days required by A and B to complete the whole work together
= $\frac{1}{\frac{1}{36}+\frac{1}{42}}=\frac{1}{\frac{7+6}{252}}=\frac{252}{13}$ days
Hence, the correct answer is $\frac{252}{13}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books