Question : A can do work in 12 days and B in 20 days. If they together work on it for 5 days and the remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

Option 1: 10 days

Option 2: 9 days

Option 3: 12 days

Option 4: 15 days


Team Careers360 10th Jan, 2024
Answer (1)
Team Careers360 11th Jan, 2024

Correct Answer: 9 days


Solution : Given: A can do a piece of work in 12 days and B in 15 days.
Time taken by A = 12 days
So, part of work done by A in 1 day = $\frac{1}{12}$
Time taken by B = 20 days
So, part of work done by B in 1 day = $\frac{1}{20}$
Work done (A + B) in 1 day = $\frac{1}{12}+\frac{1}{20}$
⇒ Work done (A + B) in 1 day = $\frac{5+3}{60}=\frac{8}{60}=\frac{2}{15}$
So, work done in 5 days = $\frac{2}{15}×5=\frac{2}{3}$
Remaining work = $1-\frac{2}{3}=\frac{1}{3}$
So, $\frac{1}{3}$ work is done by C in 3 days.
Total work is done by C = 3 × 3 = 9 days
Hence, the correct answer is 9 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books