Question : A certain number of persons can complete a work in 90 days. If there were 10 persons less, it would have taken 10 days more for the work to be completed. Find the total number of persons in the beginning.

Option 1: 90

Option 2: 110

Option 3: 85

Option 4: 100


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 100


Solution : Given,
Time taken by a certain number of persons = 90 days
The difference in days if 10 persons less = 10 days
Let the number of persons present initially be $x$.
Now, the Work done is the same
⇒ $x\times90 = (x-10)\times100$
⇒ $90x = 100x - 1000$
⇒ $100x-90x = 1000$
⇒ $x = 100$
Hence, the correct answer is 100.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books