Solution :
Given: Men employed initially $(M_1) = 200$
Let total men required to complete the work = $M_2$
Total days = 150
Work done in days $(D_1) = 50$
Remaining days $(D_2) = 100$
Work completed $(W_1) = \frac{1}{4}$
Remaining work $(W_2) = \frac{3}{4}$
We know that,
$\frac{M_1\times D_1}{W_1}=\frac{M_2\times D_2}{W_2}$
Putting the values, we get
⇒ $\frac{200\times 50}{\frac{1}{4}}=\frac{M_2\times 100}{\frac{3}{4}}$
⇒ $M_2=300$
Additional men required = 300 – 200 = 100
Hence, the correct answer is 100.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.