Question : A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?
Option 1: 115 workers
Option 2: 46 workers
Option 3: 51 workers
Option 4: 64 workers
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: 46 workers
Solution :
Given: The work can be completed in 20 days by 69 workers.
Let the more workers be $x$.
According to the question:
${M_1×D_1}$ = ${M_2×D_2}$, where $M_1, M_2$ are number of men and $D_1, D_2$ are number of days.
⇒ ${69×20}$ = ${(69+x)×12}$
⇒ $1380 = 828+12x$
⇒ $12x = 552$
⇒ $x = 46$
Hence, the correct answer is 46 workers.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.