Question : A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?

Option 1: 115 workers

Option 2: 46 workers

Option 3: 51 workers

Option 4: 64 workers


Team Careers360 1st Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: 46 workers


Solution : Given: The work can be completed in 20 days by 69 workers.
Let the more workers be $x$.
According to the question:
${M_1×D_1}$ = ${M_2×D_2}$, where $M_1, M_2$ are number of men and $D_1, D_2$ are number of days.
⇒ ${69×20}$ = ${(69+x)×12}$
⇒ $1380 = 828+12x$
⇒ $12x = 552$
⇒ $x = 46$
Hence, the correct answer is 46 workers.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books