Question : A contractor has the target of completing a work in 40 days. He employed 20 persons who completed $\frac{1}{4}$th of the work in 10 days and left. The number of persons he has to employ to finish the remaining part as per the target is:
Option 1: 10
Option 2: 20
Option 3: 40
Option 4: 30
Correct Answer: 20
Solution :
Given:
20 persons completed $\frac{1}{4}$th of the work in 10 days and left.
Now the contractor has 30 more days to complete the job.
We know,
$\frac{M_{1}\times D_{1}}{W_{1}}=\frac{M_{2}\times D_{2}}{W_{2}}$
Where $M_1$ and $M_2$ are men, $D_1$ and $D_2$ are days and $W_1$ and $W_2$ are work done
Let $n$ number of men should be added.
So, $\frac{20 \times 10}{\frac{1}{4}} = \frac{n \times 30}{\frac{3}{4}}$
$⇒20 \times 10 = n \times 10$
$\therefore n = 20$
Hence, the correct answer is 20.
Related Questions
Know More about
Staff Selection Commission Multi Tasking ...
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Get Updates BrochureYour Staff Selection Commission Multi Tasking Staff Exam brochure has been successfully mailed to your registered email id “”.