Question : A contractor has the target of completing a work in 40 days. He employed 20 persons who completed $\frac{1}{4}$th of the work in 10 days and left. The number of persons he has to employ to finish the remaining part as per the target is:
Option 1: 10
Option 2: 20
Option 3: 40
Option 4: 30
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 20
Solution : Given: 20 persons completed $\frac{1}{4}$th of the work in 10 days and left. Now the contractor has 30 more days to complete the job. We know, $\frac{M_{1}\times D_{1}}{W_{1}}=\frac{M_{2}\times D_{2}}{W_{2}}$ Where $M_1$ and $M_2$ are men, $D_1$ and $D_2$ are days and $W_1$ and $W_2$ are work done Let $n$ number of men should be added. So, $\frac{20 \times 10}{\frac{1}{4}} = \frac{n \times 30}{\frac{3}{4}}$ $⇒20 \times 10 = n \times 10$ $\therefore n = 20$ Hence, the correct answer is 20.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Rimmi and Simmi can together finish a work in 40 days. They worked together for 30 days and then Simmi left. After another 30 days, Rimmi finished the remaining work alone. In how many days Rimmi alone can finish the work?
Question : A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done $\frac{3}{5}$ part of the work, the number of men he can withdraw so that the work may still be finished in time is:
Question : A alone can do a piece of work in 30 days. He worked at it for 5 days and then B alone finished the remaining work in 10 days. In how many days B alone can finish the entire work?
Question : B and C can complete work alone in 10 days and 30 days respectively. They began the work together but B left the work after some days and C completed the remaining work in 10 days. After how many days from the beginning B left the work?
Question : Anil is 12.5% more efficient than Sachin. If Sachin alone can finish a work in 10 days, then in how many days will Anil alone finish the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile