37 Views

Question : A group of workers can complete a piece of work in 50 days when they are working individually. On the first day one person works, on the second day, another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?

Option 1: 8 days

Option 2: 9 days

Option 3: 10 days

Option 4: 11 days


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 10 days


Solution : Let the total work be 50 units and let a man complete 1 piece of work in a day.
Work done on 1st day = 1 man × 1 work/day = 1 unit of work
Work done on 2nd day = 2 men × 1 work/day = 2 units of work
Work done on 3rd day = 3 men × 1 work/day = 3 units of work
Let the whole work will be completed in $N$ days.
So, total work 1 + 2 + 3 + ..... + $N$ = 50
$\frac{N(N+1)}2=50$
⇒ $N(N + 1) = 100$
⇒ $N=10$ days(approx)
Hence, the correct answer is 10 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books