Question : A piece of work can be completed by P and Q together in 24 days, and the same piece of work can be completed by R alone in 60 days. If P and R together can do the same work in 36 days, then find the time taken by Q to complete this piece of work alone.
Option 1: $8\frac{4}{5}$days
Option 2: $29\frac{9}{13}$days
Option 3: $3\frac{6}{7}$days
Option 4: $32\frac{8}{11}$days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $32\frac{8}{11}$days
Solution : One day work of P and Q together $= \frac{1}{24}$........................(equation 1) One day work of R $= \frac{1}{60}$........................(equation 2) One day work of P and R together $= \frac{1}{36}$........................(equation 3) From equation 2 and 3, we get: One day work of P $= \frac{1}{36}-\frac{1}{60}=\frac{1}{90}$........................(equation 4) From equation 1 and 4, we get: $\therefore$ One day work of Q $= \frac{1}{24}-\frac{1}{90}=\frac{11}{360}$ Thus the work can be completed by Q alone $= \frac{360}{11}=32\frac{8}{11}$ Hence, the correct answer is $32\frac{8}{11}$.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?
Option 1: $\frac{24}{3}$ days
Option 2: $\frac{29}{3}$ days
Option 3: $\frac{32}{3}$ days
Option 4: 9 days
Question : P, Q, and R alone can do a piece of work in 5, 6, and 4 days, respectively. All three of them began the work together but Q left 1 day before completion of the work. In how many days was the work completed?
Option 1: $\frac{70}{37}$ days
Option 2: $\frac{100}{27}$ days
Option 3: $3$ days
Option 4: $\frac{80}{23}$ days
Question : S alone can do a piece of work in 14 days. T alone can do the same work in 21 days. U alone can do the same work in 28 days. Working together, in how many days will they complete the work?
Option 1: $\frac{84}{13}$ days
Option 2: $\frac{77}{13}$ days
Option 3: $\frac{71}{13}$ days
Option 4: $\frac{87}{13}$ days
Question : $\mathrm{N}_1$ alone can do 20% of a piece of work in 6 days, $\mathrm{N}_2$ alone can do 20% of the same work in 4 days, and $\mathrm{N}_3$ alone can do 50% of the same work in 12 days. In how many days can they complete the work, if all of them work together?
Option 1: 10 days
Option 2: $\frac{120}{13}$ days
Option 3: 8 days
Option 4: $\frac{120}{17}$ days
Question : Kajal can do a piece of work alone in 24 days, while Neha can do the same work alone in 40 days. Kajal started the work alone, and then after 12 clays, Neha joined her till the completion of the work. How long did the work take to be completed since Kajal started to work on it?
Option 1: $\frac{37}{4}$ days
Option 2: $\frac{39}{2}$ days
Option 3: $\frac{37}{2}$ days
Option 4: $\frac{39}{4}$ days
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile