Question : A work can be completed by 8 boys in 48 days. If 2 boys leave after working for 24 days, then how many days will be needed to complete the remaining work?

Option 1: 20 days

Option 2: 24 days

Option 3: 32 days

Option 4: 30 days


Team Careers360 15th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: 32 days


Solution : $⇒m_1d_1 = m_2d_2$
Given that 8 boys can complete the work in 48 days if 2 boys leave after working for 24 days, the number of boys for the first 24 days $m_1$ is 8, and the number of boys for the remaining days $m_2$ is 6. The number of days for the first part $d_1$ is 24. We want to find the number of days for the remaining part $d_2 $ .
$⇒ (8 × 48) = (8 × 24) + 6d_2 $
$⇒ d_2 = \frac{(8 × 48) - (8 × 24)}{6} = 32$
Hence, the correct answer is 32 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books