Question : A work can be completed by 8 boys in 48 days. If 2 boys leave after working for 24 days, then how many days will be needed to complete the remaining work?

Option 1: 20 days

Option 2: 24 days

Option 3: 32 days

Option 4: 30 days


Team Careers360 15th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: 32 days


Solution : $⇒m_1d_1 = m_2d_2$
Given that 8 boys can complete the work in 48 days if 2 boys leave after working for 24 days, the number of boys for the first 24 days $m_1$ is 8, and the number of boys for the remaining days $m_2$ is 6. The number of days for the first part $d_1$ is 24. We want to find the number of days for the remaining part $d_2 $ .
$⇒ (8 × 48) = (8 × 24) + 6d_2 $
$⇒ d_2 = \frac{(8 × 48) - (8 × 24)}{6} = 32$
Hence, the correct answer is 32 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books