Question : Aadish can complete a work in 14 days. If he worked for 8 days, then what fraction of the work would be left?
Option 1: $\frac{2}{7}$
Option 2: $\frac{3}{7}$
Option 3: $\frac{4}{7}$
Option 4: $\frac{1}{7}$
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{3}{7}$
Solution : If Aadish can complete the work in 14 days, then in 1 day he completes $\frac{1}{14}$ of the work. So, in 8 days, he completes $=8 \times \frac{1}{14}= \frac{8}{14} = \frac{4}{7}$ of the work. Therefore, the fraction of the work that is left $=1 - \frac{4}{7} = \frac{3}{7}$ Hence, the correct answer is $\frac{3}{7}$.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : A can do a piece of work alone in 15 days, while B complete the same piece of work alone in 12 days. If they work on it together for 5 days, then the fraction of the work that will be left is:
Question : Tina can do a work in 15 days and Manya can do the same work in 18 days. If they worked for 6 days, then what is the fraction of work is left?
Question : A can do a piece of work in 8 days which B can destroy in 3 days. A has worked for 6 days, during the last 2 days of which B has been destroying; how many days must A work alone to complete the remaining work?
Question : D alone can do a work in 20 days and E alone can do the same work in 25 days. If they work on it together for 8 days. then the fraction of the work that is left is:
Question : A alone can complete a work in 16 days and B alone can complete the same work in 96 days. In how many days both A and B together can complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile