Question : Aadish can complete a work in 14 days. If he worked for 8 days, then what fraction of the work would be left?

Option 1: $\frac{2}{7}$

Option 2: $\frac{3}{7}$

Option 3: $\frac{4}{7}$

Option 4: $\frac{1}{7}$


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: $\frac{3}{7}$


Solution : If Aadish can complete the work in 14 days, then in 1 day he completes $\frac{1}{14}$ of the work.
So, in 8 days, he completes $=8 \times \frac{1}{14}= \frac{8}{14} = \frac{4}{7}$ of the work.
Therefore, the fraction of the work that is left $=1 - \frac{4}{7} = \frac{3}{7}$
Hence, the correct answer is $\frac{3}{7}$.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books