Question : Aarif, Arun, and Abraham can do work in 12, 20, and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 4 days before its completion. In how many days is the work finished?

Option 1: 8

Option 2: 10

Option 3: 11

Option 4: 9


Team Careers360 25th Jan, 2024
Answer (1)
Team Careers360 27th Jan, 2024

Correct Answer: 8


Solution : Let the total time taken by them be $x$ days.
Now,
LCM of 12, 20, and 24 = 120 i.e., total work
So, efficiency of Aarif = $\frac{120}{12}$ = 10
Efficiency of Arun = $\frac{120}{20}$ = 6
Efficiency of Abraham = $\frac{120}{24}$ = 5
According to the question,
$x\times 10 + (x - 3) \times 6 + (x - 6) \times 5 = 120$
⇒ $10x + 6x - 18 + 5x - 30 = 120$
⇒ $21x = 120 + 48$
⇒ $21x = 168$
⇒ $x = 8$
Hence, the correct answer is 8.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books