Question : Aditya can complete a grill painting job in 20 hours, while Vinay can complete the same work in 15 hours. If Aditya and Vinay both work together, then in how many hours will the painting work be completed?
Option 1: $10 \frac{2}{3}$ hours
Option 2: $10$ hours
Option 3: $12$ hours
Option 4: $8 \frac{4}{7}$ hours
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: $8 \frac{4}{7}$ hours
Solution :
Given: Aditya can complete a grill painting job in 20 hours.
Vinay can complete the same work in 15 hours.
Let the total work be LCM of (20, 15) = 60 units
⇒ Efficiency of Aditya = $\frac{60}{20} = 3$ units/hour
⇒ Efficiency of Vinay = $\frac{60}{15} = 4$ units/hour
⇒ Efficiency of Aditya + Vinay = 3 + 4 = 7 units/ hour
If they work together, time taken = $\frac{60}{7} = 8\frac{4}{7}$
Hence, the correct answer is $8 \frac{4}{7}$ hours.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.