Question : Aditya can complete a grill painting job in 20 hours, while Vinay can complete the same work in 15 hours. If Aditya and Vinay both work together, then in how many hours will the painting work be completed?
Option 1: $10 \frac{2}{3}$ hours
Option 2: $10$ hours
Option 3: $12$ hours
Option 4: $8 \frac{4}{7}$ hours
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $8 \frac{4}{7}$ hours
Solution : Given: Aditya can complete a grill painting job in 20 hours. Vinay can complete the same work in 15 hours. Let the total work be LCM of (20, 15) = 60 units ⇒ Efficiency of Aditya = $\frac{60}{20} = 3$ units/hour ⇒ Efficiency of Vinay = $\frac{60}{15} = 4$ units/hour ⇒ Efficiency of Aditya + Vinay = 3 + 4 = 7 units/ hour If they work together, time taken = $\frac{60}{7} = 8\frac{4}{7}$ Hence, the correct answer is $8 \frac{4}{7}$ hours.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Question : If a man completed a work in 10 days and the same work was completed by a woman in 8 days. How many days will it take to complete if they work together?
Question : Disha takes 12 hours to copy a 75-page manuscript, while Mohit can copy the same manuscript in 10 hours. How many hours will it take for them to copy a 150-page manuscript if they work together?
Question : A can do a piece of work in 12 days and B can do the same work in 15 days. If both do the work together, then in how many days will the work be completed?
Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile