Question : After becoming a plan to operational, controlling takes place to monitor the progress.
Which relationship between planning and controlling is directed here?
Option 1: Controlling is blind without planning
Option 2: Planning without controlling is meaningless
Option 3: Planning is descriptive and controlling is evaluative
Option 4: None of the above.
Correct Answer:
Planning without controlling is meaningless
Solution :
It discovers deviations and initiate corrective measures to measure that event conform to plans. Hence planning without controlling is meaningless.