Question : After working alone for 12 days, Reena finds that only 10% of the work is completed. She employs Priya who is 40% more efficient than Reena. How many more days will they together take to complete the remaining work?

Option 1: 30 days

Option 2: 50 days

Option 3: 45 days

Option 4: 40 days


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 45 days


Solution : Since Priya is 40% more efficient than Reena
Let the efficiency of Reena be 10, then the efficiency of Priya will be 14.
Also, let the work done by Reena in days is 10% = 12 × 10 = 120 units
So, the remaining work (90%) = 1080 units
If both worked together,
1 day work for both = 10 + 14 = 24 units
Time taken by them to finish the remaining work = $\frac{1080}{24}$ = 45 days
Hence, the correct answer is 45 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books