Question : Ali, Avtar Singh, and Ashok working together can finish a work in 8 days. Ali alone can do it in 20 days and Avtar Singh alone can do it in 24 days. In how many days can Ashok alone do the same work?

Option 1: 30

Option 2: 28

Option 3: 26

Option 4: 25


Team Careers360 4th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 30


Solution : Let the total work be 1 unit.
Ali can finish the work in 20 days.
Ali's work rate = $\frac{1}{20}$ units per day.
Avtar Singh can finish the work in 24 days.
Avtar Singh's work rate = $\frac{1}{24}$ units per day.
Ali, Avtar Singh, and Ashok together can finish the work in 8 days.
The combined work = $\frac{1}{8}$ units per day.
Ashok's work rate = $\frac{1}{8} - \frac{1}{20} - \frac{1}{24}$ units per day.
Ashok's work rate = $\frac{1}{30}$ units per day.
The number of days required by Ashok to complete the work = 30 days
Hence, the correct answer is 30.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books