4 Views

Question : $\mathrm{N}_1$ alone can do 20% of a piece of work in 6 days, $\mathrm{N}_2$ alone can do 20% of the same work in 4 days, and $\mathrm{N}_3$ alone can do 50% of the same work in 12 days. In how many days can they complete the work, if all of them work together?

Option 1: 10 days

Option 2: $\frac{120}{13}$ days

Option 3: 8 days

Option 4: $\frac{120}{17}$ days


Team Careers360 16th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: 8 days


Solution : $N_1$ alone can do 20% of a piece of work in 6 days.
= 100% = 30 days
$N_2$ alone can do 20% of the same work in 4 days.
= 100% = 20 days
$N_3$ alone can do 50% of the same work in 12 days.
= 100% = 24 days
Total work = Time × Efficiency
Total work = LCM(30, 20, 24) = 120 units
Efficiency of $N_1$= $\frac{120}{30}$ = 4
Efficiency of $N_2$ = $\frac{120}{20}$ = 6
Efficiency of $N_3$ = $\frac{120}{24}$ = 5
Total of efficiency = 4 + 6 + 5 = 15
All of them working together finish the work = $\frac{120}{15}$ = 8 days
Hence, the correct answer is 8 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books