Question : Anil is 12.5% more efficient than Sachin. If Sachin alone can finish a work in 10 days, then in how many days will Anil alone finish the same work?
Option 1: $\frac{80}{7}$ days
Option 2: $\frac{70}{9}$ days
Option 3: $\frac{80}{9}$ days
Option 4: $\frac{70}{11}$ days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{80}{9}$ days
Solution : Time taken by Sachin to do the work = 10 days Efficiency of Sachin = $\frac{1}{10}$ Efficiency of Anil = $\frac{112.5}{100}$ × efficiency of Sachin = $\frac{112.5}{100}$ × $\frac{1}{10}$ = $\frac{112.5}{1000}$ = $\frac{9}{80}$ Time taken by Anil to do the work = $\frac{80}{9}$ days Hence, the correct answer is $\frac{80}{9}$ days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Sachin is 12.5 percent less efficient than Rohit. If Sachin alone can finish a work in 24 days, then in how many days will Rohit alone finish the same work?
Question : X alone can finish a work in 18 days, and Y alone can finish the same work in 9 days. If X, Y, and Z together can finish the same work in 4 days, then in how many days Z alone can finish the work?
Question : Shreyas can complete $\frac{4}{5}$th part of a work in 16 days. Ruchi is 2.5 times as efficient as Shreyas. In how many days will Ruchi alone complete the same work?
Question : Riya alone can complete a piece of work in 6 days while Siya alone can do the same work in 9 days. If they both work together, then how many days will be required to finish the work?
Question : A alone can do a piece of work in 7 days, while B alone can do it in 10 days. In how many days will they complete the same work if they both work together?