Question : Assertion: Controlling is a one-time process and does not require continuous evaluation.
Reason: Controlling involves ongoing monitoring, evaluation, and adjustment of activities.
Option 1: Both assertion and reason are true, and the reason correctly explains the assertion.
Option 2: Both assertion and reason are true, but the reason does not correctly explain the assertion.
Option 3: The assertion is true, but the reason is false.
Option 4: The assertion is false, but the reason is true.
Correct Answer: The assertion is false, but the reason is true.
Solution : The correct answer is (d) The assertion is false, but the reason is true.
This assertion is false. Controlling is not a one-time process. It involves ongoing monitoring, evaluation, and adjustment of activities to ensure they align with the planned objectives and goals. It is a continuous and dynamic function in management.
This reason is true and accurately describes what controlling involves. Controlling is an ongoing process that requires the continuous monitoring and evaluation of activities and, when necessary, making adjustments to ensure that the organization remains on track toward its objectives.