2 Views

Question : Avi alone can do a piece of work in 60 days while Prakash alone can do it in 80 days. In how many days will they finish it together?

Option 1: $\frac{250}{6}$ days

Option 2: $\frac{270}{6}$ days

Option 3: $\frac{240}{7}$ days

Option 4: $\frac{140}{6}$ days


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: $\frac{240}{7}$ days


Solution : Let the amount of work be represented by the variable $W$.
A can complete the work in 60 days.
⇒ A's work rate is $\frac{W}{60}$​ per day.
Prakash can complete the work in 80 days.
⇒ Prakash's work rate is $\frac{W}{80}$​ per day.
When they work together, their rates add up:
⇒ Combined rate = $\frac{W}{60}$ + $\frac{W}{80}$
So, the required time = $\frac{\text{Total Work}}{\text{Combined rate}}$
= $\frac{W}{\frac{W}{60}+\frac{W}{80}}$
= $\frac{1}{\frac{4+3}{240}}$
= $\frac{1}{\frac{7}{240}}$
= $\frac{240}{7}$
Hence, the correct answer is $\frac{240}{7}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books