2 Views

Question : Avi alone can do a piece of work in 60 days while Prakash alone can do it in 80 days. In how many days will they finish it together?

Option 1: $\frac{250}{6}$ days

Option 2: $\frac{270}{6}$ days

Option 3: $\frac{240}{7}$ days

Option 4: $\frac{140}{6}$ days


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: $\frac{240}{7}$ days


Solution : Let the amount of work be represented by the variable $W$.
A can complete the work in 60 days.
⇒ A's work rate is $\frac{W}{60}$​ per day.
Prakash can complete the work in 80 days.
⇒ Prakash's work rate is $\frac{W}{80}$​ per day.
When they work together, their rates add up:
⇒ Combined rate = $\frac{W}{60}$ + $\frac{W}{80}$
So, the required time = $\frac{\text{Total Work}}{\text{Combined rate}}$
= $\frac{W}{\frac{W}{60}+\frac{W}{80}}$
= $\frac{1}{\frac{4+3}{240}}$
= $\frac{1}{\frac{7}{240}}$
= $\frac{240}{7}$
Hence, the correct answer is $\frac{240}{7}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books