77 Views

Question : Benny can do a piece of work in 24 days. Chethan and David can do the same work individually in 36 and 48 days, respectively. All of them begin the work together. However, Benny leaves the work 4 days before the completion of work and Chethan leaves the work 10 days before the completion of the work. David worked till the end and completed the work. Find the number of days in which the work was completed.

Option 1: 16

Option 2: 20

Option 3: 18

Option 4: 15


Team Careers360 11th Jan, 2024
Answer (1)
Team Careers360 16th Jan, 2024

Correct Answer: 16


Solution : The rates of work per day at which Benny, Chethan, and David can complete the work are $\frac{1}{24}$,$\frac{1}{36}$, and $\frac{1}{48}$ respectively.
Let the total time taken to complete the work be $T$ days.
Benny worked for ($T - 4$) days, Chethan worked for ($T - 10$) days, and David worked for $T$ days.
The total work done is equal to 1 (as we're considering the whole work as one unit).
According to the question,
$\frac{T - 4}{24} + \frac{T - 10}{36} + \frac{T}{48} = 1$
⇒ $ \frac{6T-24+4T-40+3T}{144} = 1$
⇒ $\frac{13T}{144} = 1 + \frac{64}{144}$
⇒ $T=16$ days
Hence, the correct answer is 16.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books