Question : C1, C2 and C3 can do work alone in 10, 12, and 15 days respectively. All three of them began the work together but C2 left 2 days before the completion of the work. In how many days was the work completed?

Option 1: 3

Option 2: 7

Option 3: 5

Option 4: 4


Team Careers360 23rd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 5


Solution : C1, C2 and C3 can do a work alone in 10,12 and 15 days, respectively.
C1's 1 day's work = $\frac{1}{10}$
C2's 1 day's work = $\frac{1}{12}$
C3's 1 day's work = $\frac{1}{15}$
(C1 + C2 + C3)'s 1 day's work = $\frac{1}{10}+\frac{1}{12}+\frac{1}{15}=\frac{1}{4}$
So, they will complete the work in 4 days.
C2 left 2 days before the completion of the work.
So, remaining work = $1-\frac{1}{2}=\frac{1}{2}$
(C1 + C3)'s 1 day's work = $\frac{1}{10}+\frac{1}{15}=\frac{1}{6}$
C1 and C3 together will complete the remaining work in $\frac{\frac{1}{2}}{\frac{1}{6}}=3$ days
Total days = 2 + 3 = 5 days
Hence, the correct answer is 5.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books