Question : Dev completed the school project alone in 40 days. How many days will Arun alone take to complete the same work if he is 25% more efficient than Dev?
Option 1: 35 days
Option 2: 14 days
Option 3: 32 days
Option 4: 16 days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 32 days
Solution : Given, Dev completed the school project in = 40 days Arun is 25% more efficient than Dev. So their time ratio will be, Arun : Dev = 100 : 125 = 4 : 5 Let the days taken by Arun to complete the work be $x$. ⇒ $4 : 5 :: x : 40$ ⇒ $\frac{4}{5} = \frac{x}{40}$ ⇒ $x = 32$ Hence, the correct answer is 32 days.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : Reshma alone can do a work in 14 days. Bhavana is 40% more efficient than Reshma. The number of days, Bhavana alone will take to do the same piece of work is:
Question : After working alone for 12 days, Reena finds that only 10% of the work is completed. She employs Priya who is 40% more efficient than Reena. How many more days will they together take to complete the remaining work?
Question : A alone can complete a work in 16 days and B alone can complete the same work in 96 days. In how many days both A and B together can complete the same work?
Question : A can do a piece of work alone in 40 days. A and B together can do the same work in 10 days. C is 50% less efficient than B. In how many days can A and C together complete the same work?
Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?