Question : Direction: The following bar graph shows the production of table fans in a factory for one week. Study the bar graph and answer the given question.
The average production of table fans on Monday and Tuesday exceeds the average of table fans during the week by:
Option 1: 150 fans
Option 2: 100 fans
Option 3: 140 fans
Option 4: 200 fans
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 100 fans
Solution : According to the provided bar graph, Total number of table fans produced on Monday and Tuesday $= 260 + 540 = 800$ Number of days $= 2$ Average production of table fans on Monday and Tuesday $= \frac{\text{Total productivity on Monday and Tuesday}}{\text{Number of days}}=\frac{800}{2}=400$ Total production of table fans in the week $= 260+540+360+120+200+320 = 1800$ Required average production of table fans in the week $= \frac{1800}{6}=300$ The weekly average production is 300. Required difference = Average production on Monday and Tuesday – Weekly average production $= 400 - 300 = 100$ fans Hence, the correct answer is 100 fans.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : Direction: The graph shows the production of food grains in a country in different years. Study the graph and answer the question.
1 Views
Question : Directions: What day of the week will be on the 1st of January 2033?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile