eak thikedar road banane ke liye 15 man ko kam par lagata h ki 30 day me kam pura ho jayega lekin 24 din ke bad pata chala ki matr 1/3 road ban paya h yadi kam ko time par samapt karna h to kitne atirikt man ki zaruri hoga


Bajrangi kumar Yadav 31st Dec, 2019
Answer (1)
anshika.verma2019 19th Nov, 2020

Dear aspirant,

From the question we know that,

Work done by 15 man in 24 days is 1/3.

We need to find out,

How many people are required to do 2/3 work in 6 days.

So 1st calculate total work which is 15×24×3

And it's 2/3rd remaining work is 15×24×3×2÷3 which is = 15×24×2.

now formula is

Work =  no. Of days to complete the work × no. Of person required to complete the work.

so the remaining work to be completed is 15×24×2

And no of days in which work is to be completed= 30-24= 6 days remaining.

no. Of person required to complete the work is 15+x.

so ,

15×24×2 = 6 (15+ x)

30×24 ÷6 = 15+x

5×24.   = 15 +x

120 -15 = x

so additional no. Of people required to complete the work in remaining days is 105.



Related Questions

Amity University, B.Design Ad...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
VIT Chennai B.Sc. Admissions ...
Apply
#10 in India by NIRF Ranking | Institution of Eminence by Govt. of India | Scholarships Available
Anant National University B.D...
Apply
India's First DesignX University | Experienced Faculty
Pearl Academy B.Des Admission...
Apply
No. 1 Design & Fashion Institute by ASSOCHAM, India Today, Outlook and The Week rankings
Indian Institute of Art & Des...
Apply
Associated with FDCI, CII & IIFTI | Merit-cum-means scholarships to deserving students
UPES B.Des Admissions 2025
Apply
Ranked #46 amongst Universities in India by NIRF | Ranked #1 in Academic Reputation in India by QS World University Rankings
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books