Question : Ganesh, Ram, and Sohan can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes to finish the work is:

Option 1: 40

Option 2: 48

Option 3: 32

Option 4: 30


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 15th Jan, 2024

Correct Answer: 48


Solution : Given:
Time taken by Ganesh, Ram, and Sohan together to complete the work = 16 days
⇒ Part of work done by Ganesh, Ram, and Sohan in a day = $\frac{1}{16}$
Time taken by Ganesh and Ram to complete the work = 24 days
⇒ Part of work done by Ganesh and Ram in a day = $\frac{1}{24}$
Let the time taken by Sohan alone to do the job = $x$ days
⇒ Part of the job done by Sohan alone in 1 day = $\frac{1}{x}$
So, $\frac{1}{24}$ + $\frac{1}{x}$ = $\frac{1}{16}$
⇒ $\frac{1}{x}$ = $\frac{1}{16}$ – $\frac{1}{24}$ = $\frac{3 - 2}{48}$ = $\frac{1}{48}$
Therefore, the time taken by Sohan alone to complete the work = $x$ = 48 days
Hence, the correct answer is 48.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books