Question :
Identify the correct sequence of the Controlling process :
(A) Analysing deviations
(B) Measurement of actual performance
(C) Setting up standards
(D) Comparison of actual performance with standards
Choose the correct answer from the options below:
Option 1: (A), (B), (C), (D)
Option 2: (A), (C), (B), (D)
Option 3: (B), (A), (D), (C)
Option 4: (C), (B), (D),(A)
Correct Answer: (C), (B), (D),(A)
Solution : Following is the correct sequence of the controlling process: Setting up standards, Measurement of actual performance, Comparison of actual performance with standards, and Analysing deviations. Hence, (C), (B), (D), (A) are correct answers.
Identify the correct sequence of the Selection process :
Identify the correct sequence of steps under the Planning function :
Question : . Find the correct sequence of needs as given by Maslow in his Need Hierarchy Theory
Which of the following are advantages of the functional structure of an organisation?
Identify the correct sequence of trading \ settlement procedure :
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile