Question : If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?
Option 1: 70
Option 2: 50
Option 3: 40
Option 4: 80
Correct Answer: 50
Solution : The relation between men and the number of days is given by: $M_1D_1= M_2D_2$ Where $M_1$ and $M_2$ are men and $D_1$ and $D_2$ are days. According to the question, $25 × 140 = 70 × M_{2}$ $⇒ M_{2} = \frac{(25×140)}{70}$ $⇒ M_{2} = 25 × 2 = 50$ men ∴ 50 men will be required to complete the work in 70 days. Hence, the correct answer is 50.
Result | Eligibility | Application | Selection Process | Cutoff | Admit Card | Preparation Tips
Question : If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?
Question : P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
Question : If Arun can complete $\frac{2}{3}$rd of a work in 12 days, then in how many days can he complete $\frac{1}{6}$ th of the same work?
Question : Raman is 25% more efficient than Aman. If Aman can complete a piece of work in 25 days, Raman can complete the same work in how many days?
Question : A, B and C together can complete a work in 20 days. A and B together can complete the same work in 30 days. Then, C alone can complete the same work in how many days?