Question : If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?

Option 1: 70

Option 2: 50

Option 3: 40

Option 4: 80


Team Careers360 1st Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 50


Solution : The relation between men and the number of days is given by:
$M_1D_1= M_2D_2$
Where $M_1$ and $M_2$ are men and $D_1$ and $D_2$ are days.
According to the question,
$25 × 140 = 70 × M_{2}$
$⇒ M_{2} = \frac{(25×140)}{70}$
$⇒ M_{2} = 25 × 2 = 50$ men
∴ 50 men will be required to complete the work in 70 days.
Hence, the correct answer is 50.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books