Question : If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is:
Option 1: 38
Option 2: 28
Option 3: 19
Option 4: 17
Correct Answer: 28
Solution :
Number of men to complete the work in 8 days = 35 men
⇒ Total work = Number of men × Number of days = 8 × 35 = 280 units
So, the number of men to complete the work in 10 days = $\frac{280}{10}$ = 28
Hence, the correct answer is 28.