Question : If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is:
Option 1: 38
Option 2: 28
Option 3: 19
Option 4: 17
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 28
Solution : Number of men to complete the work in 8 days = 35 men ⇒ Total work = Number of men × Number of days = 8 × 35 = 280 units So, the number of men to complete the work in 10 days = $\frac{280}{10}$ = 28 Hence, the correct answer is 28.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : 15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
Question : 10 men can do work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:
Question : 24 men can do a piece of work in 17 days. How many men will be able to do it in 51 days?
Question : If $x$ men can do a piece of work in $x$ days, then the number of days in which $y$ men can do the same work is:
Question : 2 men can finish a work in 6 days and 3 women can finish the same work in 4 days. How many days will 1 man and 2 women finish the work if they work together daily?