Question : If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?

Option 1: 36

Option 2: 40

Option 3: 30

Option 4: 24


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 15th Jan, 2024

Correct Answer: 24


Solution : We know,
$\frac{M_1 × D_1 × T_1}{W_1} = \frac{M­_2 × D_2 × T_2}{W_2}$, where $M$ is the number of men, $D$ is the number of days, $T$ is the time in hours and $W$ is the work done.
⇒ $\frac{45 × 18 × 8}{1} = \frac{M_2 × 20 × 9}{\frac23}$
⇒ $M_2= \frac{45 × 18 × 8 × 2}{3 × 20 × 9}$
⇒ $M_2= 24$
Hence, the correct answer is 24.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books