Question : If 50 boys can finish a work in 30 days by working 6 hours per day, then how many hours per day should 25 boys work to finish that work within 24 days?

Option 1: 18 hours

Option 2: 10 hours

Option 3: 12 hours

Option 4: 15 hours


Team Careers360 9th Jan, 2024
Answer (1)
Team Careers360 12th Jan, 2024

Correct Answer: 15 hours


Solution : M$_{1}$ = 50 boys
H$_{1}$ = 6 hours
D$_{1}$ = 30 days
M$_{2}$ = 25 boys
D$_{2}$ = 24 days
M$_{1}$ D$_{1}$ H$_{1}$ = M$_{2}$ D$_{2}$ H$_{2}$
Where,
M$_{1}$ and M$_{2}$ = Number of persons
D$_{1}$ and D$_{2}$ = Number of days
H$_{1}$ and H$_{2}$ = Number of hours
According to the question, we have,
(50 × 6 × 30) = (25 × 24 × H$_{2}$)
⇒ H$_{2}$ = $\frac{(50 × 6 × 30)}{(25 × 24)}$
$\therefore$ H$_{2}$ = 15
Hence, the correct answer is 15 hours.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books