Question : If 7 people working 4 hours a day can complete a task in 14 days. The number of days taken by 12 people working 8 hours a day will be:
Option 1: $5 \frac{1}{8}$ days
Option 2: $8$ days
Option 3: $4 \frac{1}{12}$ days
Option 4: $7 \frac{1}{4}$ days
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: $4 \frac{1}{12}$ days
Solution :
Total work = Number of people × Number of hours per day × Number of days $= 7 \times 4 \times 14 = 392$
Let $x$ be the number of days required.
So, $392 = 12\times 8\times x$
$\therefore x = \frac{392}{96} = 4\frac{1}{12}$ days
Hence, the correct answer is $4\frac{1}{12}$ days.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.