12 Views

Question : If 90 men can do a certain job in 16 days, working 12 hours per day, then the part of that work which can be completed by 70 men in 24 days, working 8 hours per day is:

Option 1: $\frac{1}{3}$

Option 2: $\frac{2}{3}$

Option 3: $\frac{7}{9}$

Option 4: $\frac{5}{8}$


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{7}{9}$


Solution : According to the question:
$\frac{M_1×D_1×T_1}{W_1}=\frac{M_2×D_2×T_2}{W_2}$ Where $M_1$ and $M_2$ are men, $D_1$ and $D_2$ are days and $W_1$ and $W_2$, are work done. $T_1$ and $T_2$ are hours per day.
So, $\frac{90×16×12}{1}=\frac{70×24×8}{W_2}$
⇒ $W_2=\frac{7}{9}$
Hence, the correct answer is $\frac{7}{9}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books