Question : If A can do 20 percent of the work in 6 days, then A can complete the entire work in how many days?

Option 1: 15 days

Option 2: 25 days

Option 3: 30 days

Option 4: 60 days


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 30 days


Solution : According to the questions
20% work will be done in 6 days
⇒ 1% work will be done in $\frac{6}{20}$ days
⇒ 100% work will be done in $\frac{6}{20}×100$ days = 30 days
Hence, the correct answer is 30 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books