Question : If a man completed a work in 10 days and the same work was completed by a woman in 8 days. How many days will it take to complete if they work together?

Option 1: $\frac{38}{8}$

Option 2: $\frac{40}{7}$

Option 3: $\frac{40}{9}$

Option 4: $\frac{42}{9}$


Team Careers360 5th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: $\frac{40}{9}$


Solution : According to the question,
One day work of a man = $\frac{1}{10}$th of the total work
One day work of a woman = $\frac{1}{8}$th of the total work
When they both work together 1 day work = $\frac{1}{10} + \frac{1}{8} = \frac{5+4}{40} = \frac{9}{40}$th of the total work
They both complete the work in $\frac{40}{9}$ days.
Hence, the correct answer is $\frac{40}{9}$.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books