Question : If actual labour costs within an acceptable range of deviation, then it can be ignored. However, If it deviates by 15% then it needs immediate attention of management.
Above statement is a part of __________________________.
 

Option 1: Critical point control
 

Option 2: Management by exception
 

Option 3: Control by exception
 

Option 4: Both B and C
 


Team Careers360 1st Jan, 2024
Answer (1)
Team Careers360 9th Jan, 2024

Correct Answer: Both B and C


Solution : After identifying the major deviation, the cause need to be analysed. It is necessary to identify the exact cause so that an appropriate corrective action can be taken. This falls under management by exception or controlled by exception.
Hence Option D is correct.

Related Questions

TAPMI MBA 2025 | Technology M...
Apply
MBA Admission Open in Technology Management and AI & Data Science | NAAC A++ | Institution of Eminence | Assured Scholarships
Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates, and judiciaries
Chitkara University MBA Admis...
Apply
NAAC A+ Accredited | 100% CAMPUS RECRUITMENT
Amrita Vishwa Vidyapeetham | ...
Apply
Recognized as Institute of Eminence by Govt. of India | NAAC ‘A++’ Grade | Upto 75% Scholarships | Extended Application Deadline: 30th Jan
Great Lakes PGPM & PGDM 2025
Apply
Admissions Open | Globally Recognized by AACSB (US) & AMBA (UK) | 17.3 LPA Avg. CTC for PGPM 2024 | Extended Application Deadline: 10th Feb 2024
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books