3 Views

Question : If Ashish can complete $\frac{2}{3}$rd the work in 22 days. In how many days will he complete the whole work?

Option 1: 15 days

Option 2: 30 days

Option 3: 22 days

Option 4: 33 days


Team Careers360 25th Jan, 2024
Answer (1)
Team Careers360 26th Jan, 2024

Correct Answer: 33 days


Solution : Given: Ashish can complete $\frac{2}{3}$rd the work in 22 days.
The number of days he will complete the whole work $=22 × \frac{3}{2} = 11 × 3 = 33$ days
Hence, the correct answer is 33 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books