Question : If the deviation is minor, then it should be ignored
But if the deviation is Major, then it needs immediate action.
Which process of controlling is involved here?
Option 1: Setting performance standard
Option 2: Measurement of actual performance
Option 3: Comparison of actual performance with standard
Option 4: Analysing deviations
Correct Answer:
Comparison of actual performance with standard
Solution :
The third step into controlling process is to compare the actual performance with the standards. The extent of deviation determines the action to be taken.
Hence Option C is correct.