Question : In a field, 8 workers complete a task in 22 days. If this task is to be completed in 44 days, then how many workers will be required?
Option 1: 3
Option 2: 5
Option 3: 2
Option 4: 4
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 4
Solution : Total workers ($M_1$) = 8 Time taken ($D_1$) = 22 days Let the required workers ($M_2$) be $x$. Time taken ($D_2$) = 44 days We know that, $M_1D_1= M_2D_2$ $⇒8\times22=x\times44$ $\therefore x=4$ Hence, the correct answer is 4.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Zee and Gee can complete a task together in 24 days. If the efficiencies of Zee and Gee are in the ratio 3 : 8, respectively, then in how many days can Gee complete the task alone?
Question : 8 women can complete a work in 15 days. If 2 women are employed, then in how many days the work will be completed?
Question : 12 men can complete a work in 6 days working 4 hours per day. If 4 men work 8 hours per day, then in how many days the same work will be completed?
Question : If Ashish can complete $\frac{2}{3}$rd the work in 22 days. In how many days will he complete the whole work?
Question : 18 men can complete a work in 50 days. If 25 men are employed, then in how many days the work will be completed?