Question : Kajal can do a piece of work alone in 24 days, while Neha can do the same work alone in 40 days. Kajal started the work alone, and then after 12 clays, Neha joined her till the completion of the work. How long did the work take to be completed since Kajal started to work on it?
Option 1: $\frac{37}{4}$ days
Option 2: $\frac{39}{2}$ days
Option 3: $\frac{37}{2}$ days
Option 4: $\frac{39}{4}$ days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{39}{2}$ days
Solution : LCM of 24 and 40 = 120 Let the total work = 120 units Now, Kajal completes work in = 24 days Efficiency of Kajal = $\frac{120}{24}$ = 5 units/day Efficiency of Neha = $\frac{120}{40}$ = 3 units/day Kajal worked for 12 days before Neha Work done by Kajal = Efficiency × Number of days = 5 × 12 = 60 units Hence, 60 units of work are done by Kajal alone, Remaining work = (120 – 60) = 60 units Combined Efficiency of Kajal and Neha = (5 + 3) = 8 units/day Number of days = $\frac{60}{8}$ days = $\frac{15}{2}$ days Total number of days = $12 + \frac{15}{2}$ = $\frac{39}{2}$ days Hence, the correct answer is $\frac{39}{2}$ days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Mia and Ria can do a piece of work alone in 15 days and 10 days respectively. Mia started the work alone and then after 5 days, Ria joined her till the completion of the work. How long did the work last?
Question : S alone can do a piece of work in 14 days. T alone can do the same work in 21 days. U alone can do the same work in 28 days. Working together, in how many days will they complete the work?
Question : Seema alone can do a piece of work in 8 days and her sister Reema alone can do the same work in 24 days. If they worked together, then in how many days they will complete the work?
Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?
Question : A piece of work can be completed by P and Q together in 24 days, and the same piece of work can be completed by R alone in 60 days. If P and R together can do the same work in 36 days, then find the time taken by Q to complete this piece of work alone.
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile