1 View

Question : Kajal can do a piece of work alone in 24 days, while Neha can do the same work alone in 40 days. Kajal started the work alone, and then after 12 clays, Neha joined her till the completion of the work. How long did the work take to be completed since Kajal started to work on it?

Option 1: $\frac{37}{4}$ days

Option 2: $\frac{39}{2}$ days

Option 3: $\frac{37}{2}$ days

Option 4: $\frac{39}{4}$ days


Team Careers360 13th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $\frac{39}{2}$ days


Solution : LCM of 24 and 40 = 120
Let the total work = 120 units
Now, Kajal completes work in = 24 days
Efficiency of Kajal = $\frac{120}{24}$ = 5 units/day
Efficiency of Neha = $\frac{120}{40}$ = 3 units/day
Kajal worked for 12 days before Neha
Work done by Kajal = Efficiency × Number of days = 5 × 12 = 60 units
Hence, 60 units of work are done by Kajal alone,
Remaining work = (120 – 60) = 60 units
Combined Efficiency of Kajal and Neha = (5 + 3) = 8 units/day
Number of days = $\frac{60}{8}$ days = $\frac{15}{2}$ days
Total number of days = $12 + \frac{15}{2}$ = $\frac{39}{2}$ days
Hence, the correct answer is $\frac{39}{2}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books