Question : Mahesh, Suresh and Raju together can complete a work in 18 days. Mahesh and Suresh together can complete the same work in 72 days. Raju alone can finish the same work in how many days?
Option 1: 21
Option 2: 24
Option 3: 34
Option 4: 18
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 24
Solution : Time taken by Mahesh, Suresh and Raju together to do the work = 18 days Part of the work done by Mahesh, Suresh and Raju in a day = $\frac{1}{18}$ Time taken by Mahesh and Suresh together to do the work = 72 days Part of the work done by Mahesh and Suresh together in a day = $\frac{1}{72}$ Let $x$ be the time taken by Raju to do the work. Part of the work done by Raju in a day = $\frac{1}{x}$ $\frac{1}{72} + \frac{1}{x} = \frac{1}{18}$ ⇒ $\frac{1}{x} = \frac{1}{18} – \frac{1}{72}$ ⇒ $\frac{1}{x}= \frac{4-1}{72}$ ⇒ $\frac{1}{x}=\frac{3}{72}$ ⇒ $\frac{1}{x}= \frac{1}{24}$ ⇒ $x=$ 24 days Hence, the correct answer is 24.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : X alone can finish a work in 18 days, and Y alone can finish the same work in 9 days. If X, Y, and Z together can finish the same work in 4 days, then in how many days Z alone can finish the work?
Question : Sachin is 12.5 percent less efficient than Rohit. If Sachin alone can finish a work in 24 days, then in how many days will Rohit alone finish the same work?
Question : A, B, and C together can complete a work in 5 days. A and B together can complete the same work in 6 days. C alone can finish the same work in how many days?
Question : Kanti and Jiya together can finish a work in 3 days. If Jiya alone can finish the work in 6 days, then in how many days can Kanti alone finish the work?
Question : A and B together complete a work in 20 days, B and C together complete the same work in 30 days, and C and A together complete the same work in 24 days. In how many days A, B, and C together can complete the same work?