Question : (N + 15) persons working 9 hours a day can complete 36% of a work in 8 days. (N + 9) persons can complete the remaining work in 20 days if each of them works for 7 hours per day. Determine the value of N.

Option 1: 55

Option 2: 52

Option 3: 64

Option 4: 50


Team Careers360 9th Jan, 2024
Answer (1)
Team Careers360 14th Jan, 2024

Correct Answer: 55


Solution : Let the total work as W.
The work done is proportional to the number of persons, the number of hours worked per day, and the number of days.
We have (N + 15) persons, each working for 9 hours a day, who can complete 36% of the work in 8 days.
⇒ (N + 15) × 9 × 8 = 0.36 × W
⇒ 72(N + 15) = 0.36 × W .............................(i)
We have (N + 9) persons who can complete the remaining work in 20 days if each works for 7 hours daily.
⇒ (N + 9) × 7 × 20 = 0.64 × W
⇒ 140(N + 9) = 0.64 W ............................(ii)
Solving equations (i) and (ii), we get
N = 55 and W = 14000
Hence, the correct answer is 55.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books